LPS 1230 Issue 1.2 Requirements for fire testing of fixed gaseous fire extinguishing systems

METHODOLOGY

This approval uses the ISO test regime (“Gaseous fire extinguishing systems – Physical properties and system design – Part 1 – Annex C”) for the evaluation of agent extinguishing concentrations and nozzle performance, see 2(a).

Specific tests are conducted at the minimum design concentrations. The minimum design concentrations chosen by the system provider may include additional safety factors on this value to accommodate circumstances specific to the risk, see 2(b).

Operational details and requirements of the ISO tests are confined to Appendix A of this document.

The methodology of the overall test regime is as follows:

  1. ISO fire test regime determines the extinguishing concentrations of agent on Class A (wood and plastic fuels), and Class B (heptane) fire types
  2. LPS 1230 test regime establishes the performance of agent at the anticipated approved minimum design concentration (generally taken as being the extinguishing concentration + 30 %) on fires of a more complex and realistic configuration and checks the suitability of the delivery system and supporting design calculations by:

System

System’ is a fixed gaseous fire extinguishing system, comprising nozzles, pipe work, fixings, control valves, pressure vessels, the appropriate fire extinguishing agent and any essential fixtures to the test enclosure such as a pressure relief vent.

System provider or firm

System Provider’ or ‘firm’ denotes a company or organisation commercially and technically responsible for the correct supply and commissioning of the installed system.

Gas supplier

‘Gas supplier’ denotes a company or organisation that supplies extinguishing agent to the system provider.

Inert agent

‘Inert agent’ is a generic term used to identify non-liquefied extinguishing agents whose principle method of operation is by reducing the oxygen concentration of the atmosphere local to the fire below a level that can support combustion.

Halocarbon agent

‘Halocarbon agent’ is a generic term used to identify extinguishing agents comprising chemical substances whose principle method of operation is by removing heat from the fire and interfering with the chemistry of the combustion process.

Extinguishing concentration

Minimum concentration of extinguishing agent required to extinguish the flame of a particular fuel under experimental conditions excluding a safety factor.

Minimum design concentration

This is the concentration selected by the firm to satisfy the requirements of LPS 1230 (generally = extinguishing concentration plus 30%). System designs using concentrations less than this value are not approved.

Design concentration

‘Design concentration’ is the amount of agent including an additional safety factor on the minimum design concentration where appropriate, required for system design purposes.

Cold discharge test

Cold discharge test’ refers to a test in which the agent is released into the enclosure without a fire set.

Halocarbon agent discharge time

The ‘halocarbon agent discharge time’ shall be taken as the time between the peaks of the two ‘humps’ characteristic of the pipeline pressure profile measured by a pressure transducer located close to the nozzle.

Inert agent discharge time

The ‘inert agent discharge time’ shall be taken as the time for 95% of the agent to be discharged as determined by measurement of the oxygen depletion in the enclosure.

Fire classification

Class A fire/risk

‘Class A fire’ refers to a fire fuelled by a solid fuel source such as wood or plastic.

Class A wood fire

‘Class A wood fire’ refers to a fire comprised of a wood fuel source.

Polymeric Class A fire

‘Polymeric Class A fire’ refers to a fire fuelled by a plastic material such as polypropylene or PVC.

Class B fire/risk

‘Class B fire’ refers to a fire fuelled by a flammable liquid such as heptane.

Baffled fire

‘Baffled fire’ denotes a fire around which an obstruction has been placed to limit direct access to the fire.

Pressure relief system

‘Pressure relief system’ denotes an orifice(s) or ‘device(s)’ installed in the wall of the enclosure designed to mitigate pressure fluctuations within the enclosure to acceptable limits during discharge of the agent, whilst maintaining a satisfactory hold-time thereafter.

Extinguishing agent details

The system provider shall supply the following information:

  • Agent name (commercial and chemical).
  • Blend details and apportionment.
  • Analysis of agent taken from ‘stock batch’ from which the system containers were filled.
  • Material Safety Data Sheet for agent.

The system provider shall supply copies of the calculations used to establish:

  • The two design concentrations that will extinguish the Class A and Class B test fires respectively (if they are different).
  • Mass of agent in cylinder(s) required to achieve the design concentrations within the specified enclosure(s) 2 3 for the Cold discharges, Class A and Class B fire tests.
  • Agent discharge times for the Cold discharges, Class A and Class B fire tests.
  • Design details of the pressure relief system requirements to maintain the enclosure pressures within acceptable limits [1], whilst maintaining a satisfactory ‘hold-time’ of agent at an appropriate concentration[2] for all the cold discharges (3 off: Multiple volume; Class A concentration; and Class B concentration).
  • System installation details including pipe work plan, dimensions and nozzle specification for the Cold discharges, Class A and Class B fire tests.

The firm’s gaseous fire extinguishing system, when designed and installed as detailed below, shall extinguish all the test fires in accordance with this standard, at the first attempt.

System design and installation

Three system designs would normally be required for the fulfilment of the LPS 1230 test regime:

  • Design for the evaluation of the hydraulic calculation which discharges into multiple enclosures of different volumes
  • Design for tackling the Class A fires at the minimum design concentration
  • Design for tackling the Class B fires at the minimum design concentration

The systems shall be designed in accordance with the design manual, to provide total flooding protection of the enclosure(s) described in Section 6.1, without jeopardising the integrity of the enclosure(s) [i].

The system design and installation specification of the installed systems will be inspected for conformance with the design and installation specification submitted. Systems not installed in accordance with the submitted specification shall not be tested.

Installation of the system shall be performed by the firm or an authorised LPS 1204 installer. The system shall conform to the design manual and remain unchanged for the duration of each Class of fire.

The system design shall incorporate the minimum number of nozzles permitted by the design manual.

System requirements

  • Comparison of the analysis of the agent contained in the system with data obtained from the gas supplier shall confirm it to be that specified in the design manual.
  • The system shall be installed in accordance with the firm’s design manual.
  • Modification of the enclosure to accept the extinguishing system will be made by the firm or authorised LPS 1204 installer and be supported by appropriate design calculations.
  • The agent discharge shall not be directed at the fire source.

Operational requirements

  • During ‘cold discharge’ into multiple enclosures, the same single calculated concentration shall be achieved in each of the enclosures (-5+10% of required concentration)
  • During cold discharge into the fire enclosure with Class A and Class B minimum design concentrations:
    • The calculated concentration shall be achieved (-5+10% of required concentration)
    • The pressures within the enclosure shall be mitigated to within ± 300 Pa by the installed pressure relief device
    • The concentration of agent at 1/5 and 4/5 of the enclosure height shall be >= the extinguishing concentration 10 minutes after the end of agent discharge
    • The discharge time of the agent shall be within 20% of the stated value
  • All Class A fires shall be extinguished (no flaming) within 180 seconds of the start of agent discharge at the first attempt
  • All Class B fires shall be extinguished (no flaming) within 90 seconds of the end of agent discharge at the first attempt
  • There shall be no re-ignition of any fire for a period of ten minutes after the end of agent discharge
  • The discharge time of the agent for all fire tests shall be within 20% of the stated value for each fire type
  • Significant deviation of other design parameters observed during tests shall be reported and investigated
  • Instances of malfunction of system parts during tests shall be reported and investigated.

GASEOUS EXTINGUISHING SYSTEM TEST FIRES AND PROCEDURE

The configuration and operational procedures defined herein for the test fires are designed to produce highly repeatable fires that are suitable for the evaluation of extinguishing system performance of Halon alternative fixed gaseous fire extinguishing systems.

Two fuel types are used in the evaluation covering Class A (using wood and plastic fuels), and Class B risks. Three ‘cold discharge’ tests are required for the evaluation of some operational parameters making a total of six tests.

Geometry and construction details of multiple volume “cold discharge” test enclosure

Evaluation of the hydraulic design calculations shall require simultaneous discharge of agent into multiple enclosures of different volumes. The fire test enclosure defined in Section 6.1.2 shall be subdivided with partition walls to form 3 separate compartments with specified volumes[ii].

Geometry and construction details of fire test enclosure

The enclosure shall have nominal internal floor dimensions of 8 metres long by 4 metres wide. The roof height is chosen to suit the discharge nozzle but is not to be less than 3.5 metres high (all dimensions ±0.1 metres). The construction of the enclosure shall be such that none of the internal surfaces shall flex in reaction to pressure excursions upon agent discharge [iii]. Where sheet materials must be used, i.e. calcium silicate board on the ceiling, it shall be supported in such a way as to discourage movement.

Access to the enclosure is to be via a door (see Figure 1) and windows set in two adjacent walls will allow viewing of the fire. The door is to be constructed so as to provide a suitable location for the positioning of the extinguishing system’s pressure relief vent(s), although, if this position is considered unsuitable other reasonable locations may be used.

Ventilation of the enclosure during the fire pre-burn period is provided by an inlet situated under the fire load cell platform and outlet located high in the east wall. Both extract ducts are fitted with adjustable speed fans and shut off dampers.

With the door and ventilation dampers closed the entire room will be well sealed (no measurable leakage by the standard ‘room fan test’).

Facilities shall be in place to remotely ignite the fires.

Instrumentation details

The instrumentation described below is intended to:

  • Verify the reproducibility of the fires on which the systems are tested.
  • Collect information on the characteristics of agent discharge.
  • Collect information on the effect of agent on the fire.
  • Collect information on the effect of agent discharge on the temperature and pressure in the enclosure.
  • Collect information on the by-products of fire and agent breakdown products.

Some of the instrumentation described is not required for the approval process, providing details of other factors related to the use of gaseous extinguishing systems. Extraneous instrumentation and measurements are marked as optional as they occur in the following text[3].

Data from the prescribed sensors are to be logged at a rate of not less than 2 Hz. Where particularly fast events occur this may need to be increased.

Temperature measurement

Thermocouples shall be installed in the enclosure as follows: Plume thermocouple tree

A vertical array of six K-type thermocouples spaced 0.5 metres apart shall span from the ceiling to 0.5 metres above the floor. The array shall be positioned such that the tips of the thermocouples are located centrally above fire. The positioning of the lower thermocouples is not to interfere with the operation of the fire load cell platform. The top thermocouple shall be in contact with the ceiling.

Remote thermocouple tree

A vertical array of seven K-type thermocouples spaced 0.5 metres apart shall span from the ceiling to the floor of the enclosure. The array shall be positioned such that the tips of the thermocouples are located as shown in Figure 1. The top and bottom thermocouples shall be in contact with the ceiling and floor surfaces respectively.

Nozzle temperature measurement

A fast response thermocouple shall be located close to the discharge nozzle to monitor agent discharge details.

Pressure measurement

Agent discharge pressure

A fast response pressure transducer shall be located in the system’s discharge pipe-work at a location close to the nozzle on a T fitting. The pressure transducer shall be sized appropriately to have a range from zero bar to a value in excess of the agent’s storage pressure. An event recording rate of not less than 20 Hz shall be used.

Enclosure pressure

A differential pressure transducer having a range of ±2000 Pascals shall be installed as shown in Figure 1. An event recording rate of not less than 20 Hz shall be used.

Gas measurement

The gaseous contents of the enclosure are to be sampled as shown in Figure 1. The extract rate is to be such that the sampling delay is less than 5 seconds. The instrumentation is to have the following properties.

Oxygen

Analysers of the infrared type have proved appropriate although some extinguishing agents interfere with their operation.

Carbon monoxide

Analysers of the infrared type have proved appropriate although some extinguishing agents interfere with their operation.

Acid gas measurement

Some extinguishing agents have the potential to break down in the fire forming acidic by­products. These compounds are generally water-soluble and so may be collected by an appropriate gas absorption technique.

Agent

Agent concentrations shall be continually monitored using the most appropriate real time system for the agent. Agent concentrations during the discharge of inert gas systems may be determined from the detected oxygen depletion. Specialist instrumentation is required for the determination of halocarbon agent concentrations. Sampling points shall be located at 1/5th and 4/5th of the room height as shown in Figure 1 for single compartment ‘cold-discharge’ tests. Multiple volume discharge tests shall sample the agent from a single point within each enclosure at a height of 1150mm from the floor.

All analysers are to be calibrated prior to each test between zero and an upper value in keeping with likely detected concentrations.

Fuel mass measurement

The primary fire shall be located upon a load cell platform that is protected from the inlet airflow. The load cell is to be calibrated to an accuracy of 0.001 kg prior to each test. A range of 0 to 30 kg has proved suitable for the listed fires.

Obscuration

An obscuration meter shall be positioned across the width of the enclosure as shown in Figure 1 at a height of 1150 mm from the floor to determine the fogging characteristics of the agent.

A camera connected to a VCR positioned at the window in the longest wall, directed at the fire, shall record the proceedings of each experimental test.

Fire pre-burn ventilation

During the pre-burn period the fire is force vented to maintain oxygen levels within the enclosure. The ventilation is stopped and associated duct systems closed prior to agent discharge.

The fans in the inlet and outlet duct shall be set to provide an outflow to be determined by test (* m3s-1) whilst maintaining a pressure within the enclosure of 50 Pascals (measured in the absence of pressure relief systems).

Fire baffle specification

Details of the geometry of the baffle system are shown in Figure 2. Each fire is partially shielded by two boxes (1 m x 1 m x 0.5 m) which are open top and bottom, and a top covering plate. The bottom baffle box and top baffle plate are offset by 45o from the top baffle box creating 8 triangular voids for the passage of gas to the fire. The bottom baffle box is raised creating four additional flow paths around the base of the fire as shown in Figure 2.

The baffle boxes shall be constructed of 2mm stainless steel. The bottom baffle box shall incorporate a viewing window in one side of appropriately fire-resisting glazing. The top baffle plate shall be constructed of a single sheet of 12 mm calcium silicate board. All parts of the fire baffle shall be secured in place to stop movement during gas discharge.

Cold discharge tests

Multiple volume cold discharge test

Prior to commencing fire testing the suitability of the hydraulic design calculation shall be established by simultaneous discharge of agent into 3 enclosures of different volumes.

Each enclosure shall be sealed except for the pressure relief system installed by the system provider.

The test will establish whether the design calculation and associated equipment can deliver the same single agent concentration to each of the three enclosures.

Cold discharge test in fire enclosure

Prior to testing the system on the design fires, the agent shall be discharged into the preconditioned enclosure, with no fire.

The enclosure will be sealed except for the pressure relief system installed by the system provider. This test will establish:

  • Agent discharge time
  • Mass of agent used
  • Pressure fluctuations within the enclosure
  • Agent concentrations and hold-times in the absence of fire

Class A fire test

The configuration of the Class A fire is as shown in Figure 3 and is to be located on the load cell platform in the middle of the enclosure inside the baffle (see 6.1.6).

Class A Fire Operation

  1. The agent storage cylinders shall be weighed before connection to the rest of the system.
  2. The enclosure shall be conditioned and sealed with the fire positioned.
  • Data logging shall then start to record the initial conditions.
  1. The inlet and outlet fans shall be set to achieve the required air throughput.
  2. The video camera shall be switched on.
  3. The fire shall be lit remotely.
  • After 330 seconds from primary fire ignition the inlet and outlet fans shall be switched off and the respective dampers closed.
  • The system shall be manually operated 345 seconds after primary fire ignition.
  1. The flameout time of the fire shall be recorded.
  2. The data logging system shall run for a further 10 minutes after flameout.
  3. The empty agent cylinders shall be re-weighed after being disconnected from the rest of the system.

Polymeric Class A fire test

The cable array consists of 6 cable tray layers, each with 10 cables on it. Dimensions and arrangement of the cables are as described in Table 2 and Figure 4. The bottom of the fuel array is located 105 mm from the load cell platform.

The fuel array shall be located on the load cell platform in the middle of the enclosure inside the baffle (see 6.1.6).

LPS 1230 Issue 1.2 Requirements for fire testing of fixed gaseous fire extinguishing systems

Leave a Reply

Your email address will not be published. Required fields are marked *

Scroll to top